An investigative assessment report was conducted in September 2023 to evaluate the Veterans Memorial Auditorium (VMA) building's structure and systems. The report concluded that the building’s perimeter foundation is structurally sound, and that the elements supporting the domed roof are performing as designed. However, the subgrade below the building has settled significantly. The settlement has damaged the floor slabs, internal sewer and roof drain plumbing, and electrical systems. The report also identified several electrical and mechanical deficiencies, as well as water intrusion in key areas. Accessibility improvements are also required at various locations throughout the facility to meet current standards. Various building systems need to undergo comprehensive upgrades and safety enhancements across various critical aspects, including but not limited to the orchestra pit lift mechanism, gas lines, steel beams, sewer system, roof drains, emergency lighting and guardrails, all of which are intended to ensure the building's structural integrity and longevity. Additionally, general work like painting walls, restoring entry doors, and replacing electrical equipment will contribute to the overall functionality and visual appeal of the VMA theater building for many years to come.
Funding
The estimated $15.1M project is funded by a one-time funding allotment approved by the Marin County Board of Supervisors.
Public impacts
The facility has been closed to the public during the project.
Timeline
June 2023
- Consultant began to investigate and evaluate the VMA building.
September 2023
- The Investigative Assessment Report was submitted to the Marin County Board of Supervisors
April 2024
- Design process began
February 2025
- Construction expected to begin
December 2026
- Construction expected to be completed