On weekdays, Fairfax-Bolinas Road in West Marin is closed from Azalea Hill to Ridgecrest. On weekends, the road will be open, but traffic will be routed through a single-lane with controlled two-way access at milepost 5.73. See project webpage for details. For the project on Bolinas Road at milepost 1.0, in addition to weekday work, there will be weekend work from the 9AM to 6PM on October 5, 6, 12, and 13. See project webpage for details. Thank you for your patience while these projects progress.

2024 Road Sealant – Phase 2

Description

Overview

The 2024 Road Sealant Project (Phase 2) includes crack sealing, slurry sealing, cape sealing, microsurfacing, and refreshed traffic striping on approximately 11 miles of roadway in West Marin.  The preservation treatments selected for this project are based on the current condition of the road, utility coordination and efficient road groupings. These types of sealant projects represent relatively low-cost improvements (compared to roadway rehabilitation types of projects) that prolong the effective life of roadways in good/fair condition.

Funding

The estimate cost for this project is $2,000,000 and it will be funded by the County's Road & Bridge Fund.  

Traffic Impacts

Construction will take place during the daytime hours with traffic control measures.  Sealing work is a relatively quick compared to paving work, and typically requires only one day of significant traffic impacts per road segment.  For arterial and collector roads, expect traffic control measures and lane closures with 10 minutes traffic delays during work hours.

Property owners/residents along the roads scheduled for sealing are given advance written notifications ahead of any work that requires their road to be closed in order for them to have adequate time to prepare.

Some of the selected road are: Bear Valley Road (from Highway 1 to Sir Francis Drake Blvd): Nicasio Valley Road (from Sir Francis Drake Bvld to milepost 4.00); Lucas Valley Road (from Westgate to Big Rock); Pt. Reyes-Petaluma Road (from Platform Bridge Road to CA Highway 1); Sir Francis Drake Blvd (from Pine Hill to Pierce Point Rd).

Timeline

September 2024

  • Construction expected to be begin September 30, 2024

October 8 through November 15

  • Point Reyes Petaluma Road portion of work scheduled to occur.  Expect TRAFFIC DELAYS of up to 5 minutes with traffic control measures in place. Work hours are 8:30AM to 5PM.
  • The FIRST PHASE of work has been set for October 8 through October 11. See map below  for sections and respective dates.

Spring 2025

  • If weather is favorable, construction is expected to be complete by December 2024. However, if there are cold temperatures or persistent rain in the late fall months, the project will need to be suspended for the winter and it will restart in the spring with the expected completion of May 2025.

Point Reyes Petaluma Road work from October 8 through October 11:

Map of Point Reyes Petaluma Road section

  • October 8 (GREEN line): Point Reyes Petaluma Road from Highway 1 to near 11536 Point Reyes Petaluma Road.
  • October 9 (ORANGE line): Point Reyes Petaluma Road from near 11536 Point Reyes Petaluma Road to near 13786 Point Reyes Petaluma Road.
  • October 10 (RED line): Point Reyes Petaluma Road from near 13768 Point Reyes Petaluma Road to Buccha Basin entrance.
  • October 11 (BLUE line): Point Reyes Petaluma Road from Buccha Basin entrance to Platform Bridge Road.