Fairfax Library Safety Improvements

Description

Overview

This safety improvement project will add fire suppression sprinklers to the facility and replace existing smoke detection system with one that meets current codes and compliance. The library was built in 1976 and is in a Wildland Urban Interface Area. These improvements are part of a long term plan to protect that facility and ensure safety for patrons.

Funding

Engineer’s estimate for the project is $400,000 and funded through a Measure A bond.

Public impacts

Public access to the library will be limited during 60 days of active construction. Curbside services will be made available during the active construction period.

Timeline

March 2022

  • Anticipated completion of project plans and specifications, as well as Board of Supervisors action.

Early September 2022

  • Expected start of construction and beginning of Curbside Services

Late October 2022

  • Expected end of Curbside Services

Late December 2022

  • Anticipated end of construction