Fairfax-Bolinas Road in West Marin at milepost 5.73 (approximately 2 miles west of Azalea Hill) is single-lane access with two-way traffic controlled through one lane. This condition is at the construction zone only and will remain in place until project is completed. See project webpage for more details. Thank you for your patience while this project progresses.

Marin County Civic Center – Pole Lighting

Description

Overview

The project scope is based on urgently needed and high priority campus lighting improvements required to modernize failing systems as they approach the end of their serviceable life. Work consists of all mechanical, structural, and electrical engineering design services necessary to create and deliver plans and specifications.

Funding

Design funding estimate is $550,000 for construction services, funded by the County’s Capital Improvement Program.

Public impacts

None.

Timeline

Summer 2024 to Fall 2024

  • Design phase

Summer 2025

  • Expected start of construction phase

 