Fairfax-Bolinas Road in West Marin at milepost 5.73 (approximately 2 miles west of Azalea Hill) is single-lane access with two-way traffic controlled through one lane. This condition is at the construction zone only and will remain in place until project is completed. See project webpage for more details. Thank you for your patience while this project progresses.

Woodacre Fire Station – HVAC Replacement

This is a completed project. You are in the Archived Projects section of the website. Active projects can be found on the Projects webpage.

Description

Overview

This project replaced aging HVAC equipment to reduce future/ongoing maintenance costs, improve system reliability, and increase efficiency.  In addition to equipment replacement, the project replaced associated piping, ductwork and thermostats.

Funding

The estimated budget for this project was $310,000, funded by the County’s General Fund.

Public impacts

There were no impacts to the public during construction.

Timeline

Summer/Fall 2023

  • Design phase and project bidding

Summer 2024

  • Start of construction phase

Summer 2024

  • Project completed