Juvenile Hall Toilet Replacement

Description

Overview

This project includes replacing 5 toilet units and related plumbing, as well as enlarging the existing maintenance access points to allow for improved future maintenance needs.

Funding

Probation Department has funds available for the anticipated cost of $250,000.

Public impacts

None

Timeline

Winter 2022

  • Construction begins

Spring 2023

  • Construction complete