Hicks Valley Fire Station Reconstruction
Description
Overview
Marin County Fire Department has determined that the facility has reached the maximum capacity for required personnel. The need for proper accommodations and facilities to better house equipment, fire personnel and ultimately serve the community at large is necessary at this time.
Funding
The is currently estimated to cost $4.5 million.
Public impacts
None identified at this time.
Timeline
October 2022
- Expected completion of septic design
November through March 2023
- Expected main design phase
August/September 2023
- Expected date for start of construction phase
March 2024
- Anticipated completion of construction phase