Hicks Valley Fire Station Reconstruction

Description

Overview

Marin County Fire Department has determined that the facility has reached the maximum capacity for required personnel. The need for proper accommodations and facilities to better house equipment, fire personnel and ultimately serve the community at large is necessary at this time.

Funding

The is currently estimated to cost $4.5 million.

Public impacts

None identified at this time.

Timeline

October 2022

  • Expected completion of septic design

November through March 2023

  • Expected main design phase

August/September 2023

  • Expected date for start of construction phase

March 2024

  • Anticipated completion of construction phase