This project will seismically retrofit the Marin Center Exhibit Hall to mitigate risks to the occupants of the facility in the event of a major seismic incident at the site. The project successfully underwent FEMA environmental review.
Funding
The County was informed by CalOES in Spring 2019 that the project had been recommended for a $1.5M FEMA Hazard Mitigation Grant.
Timeline
December 2019
- Construction documents completed
August 2021
- Construction begins
June 2022
- Expected construction completion