Bretano Way Retaining Wall Replacement
This is a completed project. You are in the Archived Projects section of the website. Active projects can be found on the Projects webpage.
Description
Overview
The retaining wall along the median of Bretano Way was deteriorating at 130-132 Bretano Way. The project included demolition of the old wall and replacing it with a new, 100-foot-long wall to protect the condition of the roadway.
Funding
The construction estimate was $182,000 and was funded by the County's Road & Bridge fund.
Traffic Impacts
Egress to and from Bretano Way was not impacted. However, there were occasional temporary closures of the eastbound direction of Bretano Way at the construction zone.
Pedestrian and bicycle access was maintained during the construction phase. There was no street parking available between 126-132 Bretano Way for the duration of the construction work. Emergency vehicles were granted access at all times.
Timeline
August 5, 2024
- Construction began
August 13 and 15, 2024
- Temporary closure from noon to 2pm of the eastbound direction between 128-134 Bretano Way.
September 2024
- Completion of construction