On weekdays, Fairfax-Bolinas Road in West Marin is closed from Azalea Hill to Ridgecrest. On weekends, the road will be open, but traffic will be routed through a single-lane with controlled two-way access at milepost 5.73. See project webpage for details. Thank you for your patience while these projects progress.

2024 Road Sealant – Phase 2

Description

Overview

The 2024 Road Sealant Project (Phase 2) includes crack sealing, slurry sealing, cape sealing, microsurfacing, and refreshed traffic striping on approximately 11 miles of roadway in West Marin.  The preservation treatments selected for this project are based on the current condition of the road, utility coordination and efficient road groupings. These types of sealant projects represent relatively low-cost improvements (compared to roadway rehabilitation types of projects) that prolong the effective life of roadways in good/fair condition.

Funding

The estimate cost for this project is $2,000,000 and it will be funded by the County's Road & Bridge Fund.  

Traffic Impacts

Construction will take place during the daytime hours with traffic control measures.  Sealing work is a relatively quick compared to paving work, and typically requires only one day of significant traffic impacts per road segment.  For arterial and collector roads, expect traffic control measures and lane closures with 10 minutes traffic delays during work hours.

Property owners/residents along the roads scheduled for sealing are given advance written notifications ahead of any work that requires their road to be closed in order for them to have adequate time to prepare.

Some of the selected road are: Bear Valley Road (from Highway 1 to Sir Francis Drake Blvd): Nicasio Valley Road (from Sir Francis Drake Bvld to milepost 4.00); Lucas Valley Road (from Westgate to Big Rock); Pt. Reyes-Petaluma Road (from Platform Bridge Road to CA Highway 1); Sir Francis Drake Blvd (from Pine Hill to Pierce Point Rd).

Timeline

September 2024

  • Construction expected to be begin September 30, 2024

October 2024

  • Point Reyes Petaluma Road portion of work scheduled to occur.  Expect TRAFFIC DELAYS of up to 5 minutes with traffic control measures in place. Work hours are 8:30AM to 5PM.
  • The FIRST PHASE of work has been set for October 8 through October 11, and focuses on Point Reye Petaluma Road. See map below  for sections and respective dates.
  • The SECOND PHASE of work has been set for October 21 through October 24, and focuses on Point Reye Petaluma Road. See map below  for sections and respective dates.
  • The THIRD PHASE of work has been set for October 22 through October 30, and focuses on Nicasio Valley Road. See map below  for sections and respective dates.

November 2024

  • Project hiatus begins for the winter months, since wet weather and temperatures do not allow for the required pavement treatments.

Spring 2025

  • Expected end to project hiatus and restarting of project.

May 2025

  • Anticipated completion of project.

FIRST PHASE - Point Reyes Petaluma Road work from October 8-11:

Map of Point Reyes Petaluma Road section

  • October 8 (GREEN line): Point Reyes Petaluma Road from Highway 1 to near 11536 Point Reyes Petaluma Road.
  • October 9 (ORANGE line): Point Reyes Petaluma Road from near 11536 Point Reyes Petaluma Road to near 13786 Point Reyes Petaluma Road.
  • October 10 (RED line): Point Reyes Petaluma Road from near 13768 Point Reyes Petaluma Road to Buccha Basin entrance.
  • October 11 (BLUE line): Point Reyes Petaluma Road from Buccha Basin entrance to Platform Bridge Road.

SECOND PHASE - Point Reyes Petaluma Road work from October 21-24:

Map of point reyes road in west marin

  • October 21 (YELLOW line): Point Reyes Petaluma Road from Highway 1 to near 11536 Point Reyes Petaluma Road.
  • October 22 (GREEN line): Point Reyes Petaluma Road from near 11536 Point Reyes Petaluma Road to near 13786 Point Reyes Petaluma Road.
  • October 23 (ORANGE line): Point Reyes Petaluma Road from near 13768 Point Reyes Petaluma Road to Buccha Basin entrance.
  • October 24 (RED line): Point Reyes Petaluma Road from Buccha Basin entrance to Platform Bridge Road.

THIRD PHASE - NICASIO VALLEY ROAD work from October 22-30:

map of nicasio valley road in west marin

  • October 22 (RED line): Nicasio Valley Road from Sir Francis Drake Boulevard to 330 feet from West Nicasio Road. Nicasio Valley Road from 400 feet north of West Nicasio Road to near Fernwood Lane.
  • October 23 (GREEN line): Nicasio Valley Road from near Fernwood Lane to the Bridge at milepost 4.0.

NICASIO VALLEY ROAD work from October 25-30:map of nicasio valley road

  • October 25 (BLUE line): Nicasio Valley Road from Sir Francis Drake Boulevard to Dixon Ridge Fire Road.
  • October 28 (YELLOW line): Nicasio Valley Road from Dixon Ridge Fire Road to Fernwood Lane.
  • October 29 (GREEN line): Nicasio Valley Road from Fernwood Lane to near 2451 Nicasio Valley Road.
  • October 30 (ORANGE line): Nicasio Valley Road from near 2451 Nicasio Valley Road to near the Bridge.