Fairfax-Bolinas Road in West Marin at milepost 5.73 (approximately 2 miles west of Azalea Hill) is single-lane access with two-way traffic controlled through one lane. This condition is at the construction zone only and will remain in place until project is completed. See project webpage for more details. Thank you for your patience while this project progresses.

Who is paying for the construction?

The VMA Seismic Retrofit project total approved budget is $6.85M.  Of this total, $5.13M is expected to be reimbursed by a FEMA Hazard Mitigation Grant. The County also allocated $10 million in onetime funding in June 2023 to address other building needs beyond the seismic retrofit. This funding will cover the cost of the health/safety repairs, but additional funds will be needed to create a new seating configuration, new seats, and a sound wall. 