Airport Newsletter March 2018

Posted on March 5, 2018


March 26— Construction activity at the airport will continue this week with subgrade preparation at the airport’s aircraft apron area occurring on March 27 and 28. Asphalt pavement will occur on Thursday, March 29. Airport tenants are advised to use caution around construction workers and equipment operating at the airport.

March 28 — The contractor’s schedule has shifted and asphalt paving will now take place on Friday, March 30.  Striping will occur on Monday, April 2, followed by anchor tie-downs being installed on Tuesday, April 3. Airport tenants should be careful navigating around the construction area while crews are operating.

Close window