On weekdays, Fairfax-Bolinas Road in West Marin is closed from Azalea Hill to Ridgecrest. On weekends, the road will be open, but traffic will be routed through a single-lane with controlled two-way access at milepost 5.73. See project webpage for details. For the project on Bolinas Road at milepost 1.0, in addition to weekday work, there will be weekend work from the 9AM to 6PM on October 5, 6, 12, and 13. See project webpage for details. Thank you for your patience while these projects progress.

Redwood Frontage Road Resurfacing

This is a completed project. You are in the Archived Projects section of the website. Active projects can be found on the Projects webpage.

Description

Overview

The project will take place on a small segment (approximately 0.15 miles) of Redwood Highway Frontage Road, from the north side of Seminary Drive to the north side of the southern driveway at 580 Redwood Highway Frontage Road. Improvements for this project will include repairing road base failures, and asphalt resurfacing.

Background

Repairs to this segment of road were originally part of a larger project planned to happen after an electrical undergrounding project between Seminary Drive and Belvedere Drive; however this segment of road is deteriorating too rapidly to delay repairs further, and so it is being handled separately. The electrical undergrounding project is grant funded (Pacific Gas and Electric Rule 20A Grant) and is in the design phase, tentatively expected to go to construction in 2024.

Funding

The Engineer’s estimate for this project is $350,000.

Traffic Impacts

Ten-minute traffic delays during lane closures are expected. Every effort will be made to provide advanced notice and minimize inconvenience to residents and businesses.

Timeline

Late October 2021

  • Start of construction

Late November 2021

  • Project completion
Close window